|

TPR/April
CharltonSigns and netting warn the public to avoid an area where
asbestos-laden pipes were dug up on The Pike project. |
ARROYO GRANDE
-- Construction work has resumed on The Pike, but only in certain
areas.
Last week,
Judge Jeffrey Burke lifted the temporary restraining order he issued
Aug. 7 that brought rehabilitation work on The Pike to a complete halt
last week.
The
restraining order was issued after San Luis Obispo-based attorney
James McKiernan filed a class action lawsuit against the project
contractor, Souza Construction, on behalf of Grover Beach resident
Michael Gosnell.
The suit
charges the construction firm improperly handled and disposed of
cement pipes containing asbestos that were unearthed during a phase of
the rehabilitation project at the corner of Elm Street and The Pike.
Because the
project spans 2.5 miles, Burke ruled that Souza can resume work as
long as the construction crew doesn't come within 100 yards of the
areas where the cement pipes containing asbestos were allegedly
handled improperly.
Gosnell is a
certified asbestos supervisor who lives four blocks away from the
site.
McKiernan
said after Gosnell watched the project proceed for the first few days,
he realized that the workers were handling pipes that contained
asbestos but weren't following state or federal regulations with
regards to the handling.
"(Michael
Gosnell) went to state and local agencies with his concerns ... but it
fell on a deaf ear," McKiernan said about
Gosnell hiring a lawyer. "He
was attracted to this not as a busybody."
The attorney
said Gosnell was concerned about his health and that of his grandson,
who was staying with him when the asbestos fibers were allegedly
released into the atmosphere.
McKiernan
added that Gosnell was also concerned about the health of his
neighbors and the construction workers, who were also potentially
exposed to the fibers.
"The only way
to get (that bureaucratic) attention is to go after the man on the
street," he said. "Souza was the guy with the shovel in the dirt.
We're not necessarily saying they're the bad guys ... but we thought
the rest of the project would be handled in the same manner."
The lawsuit
charges Souza Construction didn't follow established rules that must
legally be adhered to when dealing with asbestos, something that
McKiernan said isn't that complex.
He said when
Burke heard arguments in the case yesterday, Souza's legal counsel
contended the construction firm wasn't aware that the crew would be
dealing with asbestos and didn't commit any violations at the site.
"Contractors
know in any commercial project that (asbestos) is one of the
ingredients," McKiernan added. "Just because you can't see (the
asbestos) doesn't mean that it's not there."
Asbestos
fibers that are inhaled can cause serious diseases of the lungs and
other organs that usually don't appear until 10 to 40 years after
exposure.
The fibers
are causally linked to lung cancer and mesothelioma -- a fatal disease
that affects people's ability to breathe and eventually suffocates
them.
County Health
Officer Greg Thomas said if asbestos fibers are inhaled at a high
level of concentration, "the body has a hard time getting rid of and
handling the fibers."
"Exposure is
a concentration issue. As the fibers get dispersed in the air, the
concentration levels fall because of the dispersement," Thomas added.
The doctor
wouldn't comment on whether the residents in the immediate vicinity of
the project area have a greater risk of getting cancer, but he did say
"it depends on the number and type of fibers released and the area of
distribution."
He referred
the majority of questions to the Air Pollution Control District, which
has jurisdiction over asbestos matters. APCD staff couldn't answer
questions because of the pending litigation.
However,
Thomas did say that "in general, the people working at the site are
most at risk because they're working the closest (to the asbestos)."
Although he's
not representing Souza workers who were involved with the work at Elm
and The Pike, McKiernan said "the Souza guys were guinea pigs."
McKiernan is
asking that Burke require Souza to hire a certified asbestos
consultant to oversee, inspect and investigate the work that's been
done at Elm and The Pike, with no work resuming at the four-corner
intersection until the consultant gives the site a clean bill of
health.
Once work
resumes on the entire project, the lawyer is also asking Burke to rule
that Souza must comply with all state, federal and local laws, in
particular the California Construction Safety Orders, relating to the
handling of asbestos.
"(My
argument) is that the stuff has already been buried, so let's err on
the side of the safety of the public," McKiernan said.
In addition,
McKiernan wants Souza to pay restitution to
Gosnell for lost wages and
expenses, as well as reasonable attorney fees and costs, if Burke
rules in Gosnell's favor.
Burke took
the case into submission yesterday after parties pleaded their cases.
A ruling hadn't been issued as of press time.
Staff writer
April Charlton can be reached at (805) 489-4206, Ext. 5016, or by
e-mail at
acharlton@pulitzer.net.
|